Step 1

Once the temperature and operation of the furnace is adjusted, required moulds will be loaded onto the machine.

Before mass production, the transparency of the raw glass material and the number of bubbles in the finished product must be tested. Small quantities or difficult products need to be molded and polished by hand.

Machine Line

Step 2

Fix all naked glass tops produced from the furnace onto the polishing machine.

Step 3

Polishing machine starts to process.

Step 4

After the polishing process complete, workers take off all glass tops carefully and send them to the Washing Room.

Step 5

In the Washing Room, all remaining dust after polishing is washed away by a high-pressure water jet. Only then does the product take on a crystal-clear texture. All dust and waste water in the entire industrial zone is treated by the government.

Step 6

After all glass tops are dry, all of them will be sent to the Quality Inspection Room.

Step 7

All tops will be inspected very carefully one by one. Pieces with rejections such as marks, scratches, bubbles will be sent back to the handcraft workshop for repairing.

Step 8

Finished products will be assembled with synthetic cork/natural cork and then packed in Foam or Blister packaging.

Step 9

Cartons packed in Pallets and loaded on to the container. It will enter the port directly and waiting for departure.